Fire Crash Rescue Station

Project Details

Solutions

Location

Patrick Space Force Base, FL

Client / Owner

USACE Mobile District

Size

32,250 square feet

Delivery Method

Design-Build

Construction Value

$14 million

Designing a modern and efficient facility to support the safety mission at Patrick Space Force Base’s fire station

To continue supporting the functions of the 45th Civil Engineer Squadron’s firefighting personnel and mission, Patrick Space Force Base needed a new facility that was more modern, efficient, and appropriately sized. RS&H, as part of a design-build team, RS&H was selected as the designer of record (DOR) for constructing a new fire crash rescue station facility to support both the flight line and fire trucks.

The facility is designed to be USGBC LEED Silver certified and includes a gymnasium and sauna, kitchen, dispatch center, administrative areas, 14 sleeping rooms, scuba maintenance shops, infectious control areas, hazardous material containment, compressed air systems, and high bay storage and maintenance areas for vehicles, boats, and trailers.

Experienced designers overcome project complexities

RS&H’s design team successfully addressed several areas of complexity. In addition to developing an operational layout for the unique functional areas of the building, the designers had to consider the existence of contaminated soil and potential dewatering on the project site, set-back protection due to an adjacent munitions building, and height limitations for flight clear zones on the adjacent runway. RS&H designers also delivered a structural design capable of withstanding 160-mph hurricane winds – a necessity due to the high-risk coastal location of this facility – despite the large openings required to support the facility.

Permitting prowess streamlines execution

Successfully coordinating required permits is critical for avoiding delays during the execution of a design-build project. The Fire Crash Rescue Station project required an Environmental Resource Permit and other environmental permits in coordination with the St. Johns River Water Management District because the impervious area for the site was more than 9,000 square feet. This necessitated the designers modeling the entire site utilizing the Interconnected Pond Routing (ICPR) hydrologic software.

Thanks to RS&H’s wealth of experience with permitting, including a long history of collaboration with permit authorities throughout Florida, the team successfully designed and permitted the stormwater management system on the first attempt.

Explore Exciting Career Opportunities with Us!

Related Projects

Over the past 30 years, RS&H has supported continuous, data-driven sustainability performance improvement for the Defense Commissary Agency (DeCA), which operates a worldwide network of over 280 commissaries and central distribution centers.

Federal

After leading the concept design workshop and project development phase, RS&H, as part of a joint venture (JV), was selected to lead the P407 Littoral Innovation and Prototype Facility design at Naval Support Activity (NSA) Panama City, FL.

Federal

In an effort to fortify the U.S. Navy’s training processes and procedures for sailors, the U.S. Army Corps of Engineers (USACE) Japan District turned to RS&H, as part of a joint venture (JV), to develop a full design package for a new Ship Handling and Combat Training Facility (SHCTF) at Command Fleet Activities (CFA) Yokosuka.